The crew also doesn't seem to be working off of the plans that were drawn, and so the porch is also a foot narrower than it should be. The construction manager from Blitz came down on Tuesday and told us that the porch would be fixed.
The plumbers arrived on Monday but were surprised to find the house was up. They came prepared to do the rough in plumbing with the trackhoe. They refused to hand dig for the rough-in, so they just left for the day.
Mike called plumbing company and was told that a crew would be sent out Tuesday to hand dig and do the rough in plumbing. That part is done and inspected and we are ready for the concrete guy to come back and fill in the plumbing trenches get ready to pour the concrete.
We had planned to pour concrete early this week, but with the plumbing delay and the holiday we now plan to pour concrete on Tuesday morning. Hopefully by the end of the week, the Blitz construction crew will be back to finish the shell.
We have the windows and doors on site and they will be installed by the construction crew.
When all of that is done Mike and I can start the framing on the inside.
Rough in plumbing completed |
Brenda went to the Bartlett fireworks show last night and met some family and friends from church. I didn't go because I had worked all day yesterday and was too tired. I was in bed before 8:30 PM.
If the show was as good as it was last year. I'm sure she had a good time.
I will continue to keep you informed as the house and Brenda's job progresses.
Tata for now.
1 comment:
It looks like things are coming right along - I understand construction delays. Seems like they always happen and you just have to go with the flow. Tell Brenda Congratulations on the job - hope she gets to work as much as she would like. We went out on the lake and watched the fireworks again this year - the city did a very nice job. Hope things continue to move along and will stay tuned for updates.